On March 15th , the Iraq 2*60T/H cement grinding station project contracted by Sinoma Tianjin has been issued FAC, which signifies the acceptance by the employer and enters into one-year quality guarantee period.
This project took effective on June 28th ,2012. At the end of June, 2013, the first shipments of equipments were delivered to the site; on September 28, the second shipment of equipment was delivered to the site; on January 16th, 2014, cement mill 426 was put into production; on February 18th, cement mill 416 was successfully put into production; on February 27th, cement mill 426 system passed 72-hour performance test; on March 8th, cement mill 416 system has passed 72-hour performance .
This project was Sinoma Tianjin’s first project in Iraq. The dedication and solidarity of the team has won his praise from the employer.