Rotary Kiln Shell Fixed and Welded Successfully for Benin Project

Pubdate:2014-01-07

With the efforts of the project team, the last piece of rotary kiln shell was successfully lifted, fixed and welded on January 1st 2014. To achieve this goal, the project management people and construction team worked overtime at the expense of their New Year vacation time.

 

This work is an important milestone for the construction of the clinker production line. The Benin project team will continue their efforts to complete the clinker production line on time.

 